UPDATES
JUST COMPLETED
- The kitchen, pantry, laundry,
staff bath and storage rooms that occupy about 25% of
the first floor of the Phase Two Housing Building is now
construction complete!
- Funds have been given to
purchase a commercial washer and dryer for the laundry
room!
- 60% of the block work has been
completed on the second floor of the Phase Two Housing
Building!
STILL PENDING
- Furnish the commercial kitchen
with cabinets, counters, sinks, appliances, hood, etc.
- Complete block work on the second
floor of the Phase Two Housing Building
- Finish work on the stairwell in the
housing building
- Build retention wall on the back
side of the property
- Complete about 100 feet of the
security wall on the back corner of the property
- Build security entrance near the
street
- Condition a parking area on the
front side of the building
- Recondition the main road
NEXT PHASE... PHASE THREE ATRIUM
CONSTRUCTION BEGINS IN 2018. So far, we have two
teams confirmed for 2018 that will be working on the Phase
Three Atrium construction. The Atrium connects the 1st and 2nd
buildings. The Atrium will include reception, lobby and open
area for meetings and meals. The Atrium will feature a
mezzanine bridge that will connect the buildings 1 and 2 on
the second floor.
With the Atrium complete, the LARTC will be
functionally complete to equip leaders, train teachers and produce
resources. There are two future phases planned that will
increase the training and
administration areas and
provide staff housing.
Thank you for your prayers and giving
(http://s1.ag.org/lartc)!
|
The latest construction updates
and photos!
|